Oct-Dec 2023
Summary of significant progress includes:
- Pre-engineered metal building construction about 98% completed
- Exterior concrete stoop and pads poured across the entry and exit doors
- Architectural and professional services for the interior plan details including doors and framing
- Received and reviewed proposals for the exterior and interior doors
- Received and reviewed proposals for the interior framing and other trades
- Connected the addition building’s roof with the existing roof; drainage re-routed