Jul – Sep 2023
Summary of significant progress includes:
- Pre-engineered metal building construction about 90% completed
- Insulation of the roof and exterior walls completed
- HVAC equipment procured by the sub-contractor
- Architectural and professional services for the interior plan details
- Continuing to seek and review proposals for additional trades for the interior
- Connecting the new building with the existing building of different material needed multiple expertise to create a solution.