Apr-Jun 2023
Summary of significant progress includes:
- Engineering, architectural, and professional services and project plan details
- Sitework with underground drainage
- Electrical and plumbing utility layout
- Concrete footing and slab
- Pre-engineered metal building construction
- Detailed specifications and proposals for additional trades
- Challenge encountered:
- Distant bathroom drain could not be connected to the existing septic tank; a new septic tank
- needed to be installed with some onsite changes and quick decisions; county office approved the new setup.