Construction Progress: April through June 2023

Apr-Jun 2023

Summary of significant progress includes:

  • Engineering, architectural, and professional services and project plan details
  • Sitework with underground drainage
  • Electrical and plumbing utility layout
  • Concrete footing and slab
  • Pre-engineered metal building construction
  • Detailed specifications and proposals for additional trades
  • Challenge encountered:
  • Distant bathroom drain could not be connected to the existing septic tank; a new septic tank
  • needed to be installed with some onsite changes and quick decisions; county office approved the new setup.