Construction Progress: Jul through Sep 2024

Jul– Sep 2024

Summary of significant progress includes: 

  • North exterior face completed with brickwork; concrete patio and electrical service area 
  • Interior wall framing mostly completed; delay of several weeks due to building inspector’s feedback on fire-rated walls; issue is resolved by architect’s revised drawing and related additional work on framing 
  • Interior details including flooring material, wall and door colors,  
  • Mechanical, electrical and plumbing rough-in continued; fixtures selection in progress 
  • Propane tank location revised based on the Dallas County inspector’s feedback 