Construction Progress: Oct through Dec 2024

Oct– Dec 2024

Summary of significant progress includes:

  •  Plumbing rough-in with some modifications completed and inspected 
  • Mechanical rough-in inspection revealed fire-damper needs; it required an update to the architectural drawing and submission; completed 
  •  New Propane tank installed and connected; heating started for the winter 
  • Interior wall framing changes at the fire-rated wall completed; backing boards in progress 
  • Site grading and clean up; exterior doors got painted 